Equal and Non-Discriminatory Treatment

December 2nd, 2016 by James Goudie KC in Decision making and Contracts

The Advocate General’s Opinion on 1 December 2016 in Case C-296/15, Medisanus v Murska Sobota, restates the requirement for contracting authorities to treat economic operators equally and non-discriminatorily. The Advocate General said:-

“76.    Under Article 2 of Directive 2004/18, the contracting authorities are required to treat economic operators equally and non-discriminatorily.

  1. According to the Court’s case-law, in application of the principle of equal treatment as between tenderers, the aim of which is to promote the development of healthy and effective competition between undertakings taking part in a public procurement procedure, all tenderers must be afforded equality of opportunity when formulating their tenders, which therefore implies that the tenders of all competitors must be subject to the same conditions.
  2. Strictly speaking, the national origin requirement distinguishes not between economic operators but between products, by excluding medicinal products not manufactured on the basis of Slovenian plasma.
  3. Nonetheless, it has consistently been held that the principle of equal treatment, of which Article 2 of that directive is a particular expression, prohibits not only overt discrimination based on nationality but also all covert forms of discrimination which, by applying other distinguishing criteria, in fact achieve the same result.
  4. A clause requiring that a medicinal product be manufactured on the basis of plasma collected in the national territory is liable to operate mainly to the detriment of economic operators of other Member States, since they will find it more difficult to have access to plasma collected in the national territory than the economic operators of the Member State concerned.
  5. In the circumstances of the main proceedings, the discriminatory effects of that national origin requirement are all the more apparent because the ZTM, a Slovenian body, is in practice the only economic operator capable of supplying medicinal products manufactured on the basis of Slovenian plasma, which precludes all operators in other Member States.
  6. I conclude from the foregoing that Article 2 of Directive 2004/18 of Directive 2004/18 must be interpreted as meaning that it precludes the national origin requirement.”

The national origin requirement was also contrary to Article 34 TFEU, as was a priority supply requirement.

The Advocate General also stated that the Hamburg Waste exemption was not applicable.  The Advocate General said:-

“72.    That judgment concerned a contract concluded for a period of 20 years between the City of Hamburg (Germany) and four Landkreise, for the purpose of establishing long-term cooperation between those local authorities for reciprocal treatment of waste. Thus, that contract, which had been concluded without launching a call for tenders, formed both the basis and the legal framework for the future construction and operation of facility intended to perform a public service, namely thermal incineration of waste. The Court held that such a contract was not required to be the subject matter of a prior call for tenders.

  1. Admittedly, the circumstances of the main proceedings bear certain resemblances to those of the judgment in Commission v Germany, and in particular the public nature of the contracting parties, namely Murska Sobota general hospital and the ZTM. However, in that judgment it was not the Court’s intention to exclude all contracts between public entities from the rules applicable to public contracts, but only those forming both the basis and the legal framework for long-term co-operation with the intention of carrying out a public service. That is not the case of the contract at issue in the main proceedings, the object of which is limited to the occasional supply of medicinal products manufactured on the basis of human plasma.
  2. Consequently, I consider that the contract at issue in the main proceedings does not come within the exception established by the Court in the judgment in Commission v Germany.”

 

 

 

 

Legitimate expectation

October 25th, 2016 by admin in Decision making and Contracts

In Infinis Energy Holdings Ltd v HM Treasury (2016) EWCA Civ 1030 the Court of Appeal held that the decision to remove the exemption for renewable source energy from the climate change legacy did not breach the EU principles of legitimate expectation and proportionality. In order to give rise to a legitimate expectation there had to be an undertaking, or an assurance that was precise, unconditional, consistent and lawful, not a vague indication, and the expectation had to be reasonable.

 

Management & Investment of Pension Funds

September 26th, 2016 by James Goudie KC in Decision making and Contracts

The Local Government Pension Scheme (Management and Investment of Funds) Regulations 2016, S.I. 2016/946, made 21 September 2016, coming into force 1 November 2016, make provision, by Regulations 2 & 3, that restrictions imposed by the Regulations bind authorities which have the General Power of Competence (under Section 1 of the Localism Act 2011 or Section 5A (1) of the Fire and Rescue Services Act 2004) in the exercise of that power.

 

 

Abandoning Statutory Rights

July 20th, 2016 by James Goudie KC in Decision making and Contracts

With respect to contracting out of or waiving statutory rights, the Privy Council per Lord Clarke, enunciated the following principles in Bahamas Oil Refining Co v The Owners of the Cape Bari [2016] UKPC 20:-

  1. Someone may by their conduct contract out of or waive a provision of an Act of Parliament intended for their benefit and exclude a legal right: paragraph 23;
  2. For a party to be held to have abandoned or contracted out of valuable rights arising by operation of law the contractual provision relied upon must make it clear that this is what was intended: paragraph 31;
  3. This principle applies in very many contexts: paragraph 32;
  4. A Court is unlikely to be satisfied that valuable rights arising by operation of law have been abandoned unless the terms of the contract make it sufficiently clear that that was intended: paragraph 33;
  5. The more valuable the right, the clearer the language will need to be: ibid.

 

Equal treatment

July 18th, 2016 by James Goudie KC in Decision making and Contracts

In Gallaher Group Limited v Competition and Markets Authority (2016) EWCA Civ 719 the Court of Appeal considered the application of the EU and common law principle of equal treatment.  Lord Dyson MR said, at paragraph 39: “In my view, the fact that one party (A) has made a request for more favourable treatment and another party (B) has not done so will rarely amount to a good reason for not treating them as being in a relevantly comparable position for the purposes of equal treatment if they are in fact otherwise in relevantly comparable positions”.

On the matter of objective justification for not replicating in favour of the appellants the approach adopted in relation to another because that approach had been mistaken, the question (paragraph 53) is whether the difference in treatment is “fair in all the circumstances”. “The fact that a decision by a public authority is mistaken is not a “trump card” which will always carry the day so as to permit the authority not to replicate the mistake regardless of the circumstances. …  the question is whether there has been unfairness on the part of the authority having regard to all the circumstances. The fact that there has been a mistake may be an important circumstance. It may be decisive. It all depends.”

Lord Dyson continued, at paragraph 54: “The law relating to legitimate expectation is of some assistance here. It is well established that a legitimate expectation cannot be relied on to require a public authority to act in breach of its statutory duty or to do something ultra vires. … But the courts have considered whether a public authority may defeat a legitimate expectation where the expectation has been created by mistake. In R v Department for Education and Employment, ex p Begbie [2000] 1 WLR 1115, 1127B-D, Peter Gibson LJ said that, where the court is satisfied that a mistake has been made, the court should be slow to fix the public authority permanently with the consequences of a mistake. But importantly, he went on to say that the question of whether the authority should be permitted to resile from a mistaken statement depends on whether that would give rise to unfairness amounting to an abuse of power. The law relating to legitimate expectation is grounded in fairness.” Longmore and Lloyd Jones LJJ agreed.

 

Public contract award procedures

July 15th, 2016 by James Goudie KC in Decision making and Contracts

In Case C-6/15, TNS Dimarso NV v Vlaams Gewest, Judgment on Bastille Day 2016, the ECJ has held that Article 53(2) of Directive 2004/18/EC on the coordination of procedures for the award of public works contracts, public supply contracts and public service contracts, read in the light of the principle of equal treatment and of the consequent obligation of transparency, must be interpreted as meaning that, in the case of a public service contract to be awarded pursuant to the criterion of the most economically advantageous tender in the opinion of the contracting authority, that authority is not required to bring to the attention of potential tenderers, in the contract notice or the tender specifications relating to the contract at issue, the method of evaluation used by the contracting authority in order to specifically evaluate and rank the tenders. However, that method may not have the effect of altering the award criteria and their relative weighting.

The ECJ stated the principles as follows:-

“… it should be noted that where the contracting authority decides to award a contract to the most economically advantageous tender, under Article 53(2) of Directive 2004/18, it must specify in the contract notice or the tender specification the relative weighting it gives to each of the award criteria chosen in order to determine the most economically advantageous tender. That weighting may be expressed by providing for a range with an appropriate maximum spread. Where, in the opinion of the contracting authority, weighting is not possible for demonstrable reasons, the contracting authority shall indicate in the contract notice or tender specifications or, in the case of a competitive dialogue, in the descriptive document, the criteria in descending order of importance.

As stated in recital 46 of Directive 2004/18, the purpose of those requirements is to enable all tenderers to be reasonably informed of the criteria and arrangements which will be applied to identify the most economically advantageous tender. In addition, they reflect the duty of the contracting authorities under Article 2 of the directive to treat economic operators equally and non-discriminatorily and to act in a transparent way.

According to settled case-law, the principle of equal treatment and the obligation of transparency entail, in particular, that tenderers must be in a position of equality both when they formulate their tenders and when those tenders are being assessed by the contracting authority …

Thus, the Court has held that the subject matter of each contract and the criteria governing its award must be clearly defined from the beginning of the award procedure … and that a contracting authority cannot apply, by way of award criteria, sub-criteria which it has not previously brought to the tenderers’ attention … Similarly, the contracting authority must interpret the award criteria in the same way throughout the procedure …

Those requirements apply, in principle, mutatis mutandis to contracting authorities’ obligation to indicate, in the contract notice or the tender specifications, the ‘relative weighting’ of each of the award criteria. Thus, the Court has held that a contracting authority may not, in principle, apply weighting rules which it has not previously brought to the tenderers’ attention …

In particular, the relative weighting of each of the award criteria must, subject to the third subparagraph of Article 53(2) of Directive 2004/18, be clearly defined from the beginning of the award procedure, thus enabling tenderers to establish objectively the actual importance given to an award criterion relative to another during their subsequent evaluation by the contracting authority. Similarly, the relative weighting of each of the award criteria cannot be changed throughout the procedure.

Nonetheless, the Court has accepted that it is possible for a contracting authority to determine, after expiry of the time limit for submitting tenders, weighting factors for the sub-criteria which correspond in essence to the criteria previously brought to the tenderers’ attention, provided that three conditions are met, namely that that subsequent determination, first, does not alter the criteria for the award of the contract set out in the tender specifications or contract notice; secondly, does not contain elements which, if they had been known at the time the tenders were prepared, could have affected their preparation; and, thirdly, was not adopted on the basis of matters likely to give rise to discrimination against one of the tenderers …

However, neither Article 53(2) of Directive 2004/18 nor any other provision thereof lays down an obligation on the contracting authority to bring to the attention of potential tenderers, by publication in the contract notice or in the tender specifications, the method of evaluation applied by the contracting authority in order to effectively evaluate and assess the tenders in the light of the award criteria of the contract and of their relative weighting established in advance in the documentation relating to the contract in question.

Nor is such a general obligation apparent from the case-law of the Court.

The Court has held that an evaluation committee must be able to have some leeway in carrying out its task and, thus, it may, without amending the contract award criteria set out in the tender specifications or the contract notice, structure its own work of examining and analysing the submitted tenders …

That leeway is also justified by practical considerations. The contracting authority must be able to adapt the method of evaluation that it will apply in order to assess and rank the tenders in accordance with the circumstances of the case.

In accordance with the principles governing the award of contracts provided for in Article 2 of Directive 2004/18 and in order to avoid any risk of favouritism, the method of evaluation applied by the contracting authority in order to specifically evaluate and rank the tenders cannot, in principle, be determined after the opening of the tenders by the contracting authority. However, in the event that the determination of that method is not possible for demonstrable reasons before the opening of the tenders … the contracting authority cannot be criticised for having established it only after that authority, or its evaluation committee, reviewed the content of the tenders.

In any event, pursuant to the principles governing the award of contracts … the determination by the contracting authority of the method of evaluation after the publication of the contract notice or the tender specifications cannot have the effect of altering the award criteria or their relative weighting.”

 

Contracts

July 4th, 2016 by James Goudie KC in Decision making and Contracts

There have been a number of important recent Court of Appeal decisions on the law of contract, including in relation to the following propositions: (1) if a party to an agreement promises to make extra payment in order to secure the other party’s promise to perform his existing contractual obligation to provide services and, as a result, secures a benefit, then the benefit is capable of constituting consideration for the promise: MWB Business Exchange Centres v Rock Advertising (2016) EWCA Civ 553 (“MWB”); (2) the fact that a contract contains a clause requiring any amendment to be in writing and signed by both parties does not prevent them from later making a new contract varying the contract by an oral agreement, or by conduct: Globe Motors v TRW Lucas Varity Electric Steering [2016] EWCA Civ 396, MWB; (3) a contract may be concluded where there is acceptance by the claimant by conduct of a written agreement signed by the defendant stated to be binding only after signature by the claimant: Reveille Independent LLC v Anotech International (2016) EWCA Civ 443.

 

Local authorities, procurement and not profit organisations

June 2nd, 2016 by Peter Oldham QC in Decision making and Contracts, Judicial Control, Liability and Litigation, Land, Goods and Services

Local authorities often procure contracts from non-profit organisations (NPOs). Assume an NPO brings a claim under the Public Contracts Regulations 2015 claiming that something went wrong in a procurement, such that there is an automatic suspension preventing the contract being entered into. Say the authority then applies to Court to set the suspension aside.  How does the American Cyanamid test apply where the claimant is an NPO?  In A v B TCC 27 May 2016, the Technology & Construction Court returned to this question.

Readers will recall that on an application to lift the suspension under the PCR, Cyanamid means that the Court will consider whether there is a serious issue to be tried; whether damages are an insufficient remedy; and whether the balance of convenience lies with maintaining the suspension. The modern trend is to see the adequacy of damages as one of the factors relevant to the balance of convenience, rather than as a separate stage.

In Bristol Missing Link Ltd v Bristol City Council [2015] PRST 1470, the claimant was an NPO providing domestic violence and abuse support services to the local authority. Its tender made no allowance for any profit, so that damages would be nominal at most. The suspension was not lifted. Coulson J said at [55]:-

 “In my view, a non-profit-making organisation, which has bid for a contract making no allowance for profit at all, and a minimal amount for overheads, is entitled to say that, in such circumstances, damages would not be an adequate remedy.”

In A v B, the claimant was an NHS trust, and so also an NPO.  The defendant was a procuring CCG. On the CCG’s application to set aside the suspension, Stuart-Smith J distinguished Bristol. He said that the mere fact that the Trust was an NPO did not mean that damages would be an inadequate remedy.  Moreover in Bristol, the claimant’s business stood to be wiped out if it lost the tender.  Here by contrast, the Trust stood to lose only 10% of its work.  After considering other factors relevant to the balance of convenience, the judge set the suspension aside.

So the first point to take away is that merely because the claimant is an NPO will not mean that it gets over the hurdle of showing that damages would be an insufficient remedy. As ever, it is a question of fact.

And as to that, the Courts have recently made it clear that, on an application to discharge the suspension, simple assertions, by either party, about where the balance of convenience lies will not be enough to make their case. Solid evidence is normally needed e.g. OpenView Ltd v Merton LBC [2015] BLR 735; Counted4 CIC v Sunderland CC 164 Con LR 230. And that’s the second point to take away.

Peter Oldham QC

 

 

Concession Contracts

April 7th, 2016 by James Goudie KC in Decision making and Contracts

On 18 April 2016 the Concession Contracts Regulations 2016, S.I. 2016/273 (“the Concessions Regulations”), come into force. They implement the 2014 Directive, 2014/23/EU, on concession contracts (“the Concessions Directive”). They extend to England and Wales, and Northern Ireland.

The Concessions Regulations impose obligations on “contracting authorities” (and utilities) concerning the award of “concession contracts”. “Contracting authorities” include local authorities. “Concession contracts” embrace both works and services concessions. They are contracts for “pecuniary interest” concluded in writing under which the consideration consists either solely in the “right to exploit” the works/services or in that right together with payment, and that meet a risk requirement.  That is that the award of the contract shall involve the transfer to the concessionaire of an “operating risk” and that the risk transferred shall involve “real exposure to the vagaries of the market”.

There is a high threshold: £4,104,394. However, below the threshold general EU Treaty principles will apply if the low threshold of a cross-border interest is applicable.

Parts 1 and 2 of the Concession Regulations set out their scope and principles. Part 3 contains rules on the award of concession contracts. Chapter 1 contains obligations relating to the publication of concession notices and concession award notices (Regulations 31 to 33), the electronic availability of concession documents (Regulation 34) and the prevention of corruption and conflicts of interest (Regulation 35). Chapter 2 of Part 3 contains provisions relating to technical and functional requirements of concession contracts (Regulation 36), the selection and qualitative assessment of candidates (Regulation 38) and award criteria (Regulation 41).

Part 4 contains rules on the performance of concession contracts, including provisions relating to subcontracting (Regulation 42), the modification and termination of concession contracts (Regulations 43 and 44) and reporting requirements (Regulation 45). Part 5 contains provisions about remedies.

 

 

Implied contractual term as to planning consent

March 4th, 2016 by James Goudie KC in Decision making and Contracts

Walter Lilly & Co Ltd v Clin [2016] EWHC 357 (TCC) concerned a contract for the demolition, refurbishment and reconstruction of a property to form a single residence. Whilst the works were underway, the local planning authority, the Royal Borough of Kensington and Chelsea, wrote to the parties stating that the extent of the demolition was such that conservation area consent was required.  Edwards-Stuart J held that a term should be implied into the contract that the owner would provide the authority with the information its planning officers required in order to process the application for consent, but not a term that consent should be obtained. This was not within the owner’s control.

The Judge said:-

“54.    The reasonable man in the position of the parties would, in my view, have in mind that, in general, a person who wishes to develop his land will know either that he is likely to need planning permission or, in the case of a residential development, that he must satisfy himself that the development proposed is exempt from the requirement for planning permission. The same applies to conservation area consent where the property is in a conservation area.

  1. In principle, planning permission needs to be obtained in advance: it can be obtained retrospectively, but this is obviously risky. But even when applied for well in advance, everyone knows that planning permission cannot be taken for granted. For example, the prospects of planning permission being given may depend to a large extent on the attitude of owners of neighbouring properties. Similar considerations may apply to conservation area consent.
  2. In this case it seems to me to be obvious that the parties must have intended that someone should have the responsibility for applying for planning permission. This is not a case where, because nothing is said expressly in the contract, the parties could have intended that nothing should happen about planning permission: planning permission had to be obtained in order for the development to go ahead. In addition, it seems to me that it would be equally obvious to an informed bystander that the party best placed to obtain planning permission is the employer, not least because he is the party who knows well in advance what he wants to do. The contractor does not find that out until he is invited to tender, by which time it may be too late for planning permission or conservation area consent to be obtained in time. Any reasonable person would know that a failure to make a timely application for the necessary permission or consent might well result in delay (unless of course the contractor has indicated that is prepared to take the risk of carrying out the work without that permission or consent).
  3. It appears to be common ground that the primary responsibility for applying for planning permission rests with the employer. The essential point at issue between the parties is whether a term should be implied to the effect that the employer will ensure that planning permission is obtained, or whether there should be a more limited obligation – for example, to exercise reasonable diligence to obtain the necessary planning permission.”

The Judge said, at paragraph 67, that he could see no justification for imposing on either party sole responsibility for the consequences of capricious conduct by the local authority. For the contract to work it was not necessary that either party alone should bear that risk. The contract can work just as well if that risk is left to lie where it falls. It is a situation where, since the contract has not provided how the risk should be borne, no provision should be made.

The Judge concluded that the correct formulation of the implied term was not one for which either side contended.